When should you start building a pool to swim by summer?
To swim by Memorial Day 2027 (May 31), finish design and permits by mid-January and start excavation in February. Construction takes 10 to 12 weeks on a typical lot and up to 16 weeks with heavy rock, HOA review or wet weather. Starting design in November or December leaves that margin.
The latest practical start is early March for the dig, which means design by early February. After that, a Memorial Day swim depends on an easy lot and good weather. Starting in winter also helps with approvals: HOA architectural committees tend to review and approve plans faster in the winter months than in peak spring season, so a winter submittal is less likely to delay your start. Our week-by-week build timeline shows what happens at each stage.
What does a summer 2027 pool schedule look like?
This is the schedule for a February dig on a typical lot. Every month the dig slips moves the swim date by about the same amount.
-
Nov – Dec 2026
Consultation & 3D design
We walk the lot, measure, and design the pool in 3D. Revisions happen on screen, before anything is built.
-
Late Dec – Jan 2027
Contract, engineering & permits
Soil study and engineering where the lot needs it, the city or county permit, and your HOA submittal.
-
February
Excavation & steel
Dig, form, tie steel and rough in plumbing, then inspection. Rock excavation happens here.
-
March
Gunite & cure
The shell is shot and watered through its cure so it reaches full strength.
-
April
Tile, coping, deck & equipment
Waterline tile, coping, decking, and the pump, filter, heater and automation.
-
May
Interior finish & startup
PebbleTec interior, fill, water balance, and a walkthrough of your equipment before your first swim.
What is the latest you can start and still swim by Memorial Day?
Counting back from May 31, 2027, a typical 12-week build needs to break ground by early March. A build with rock excavation, a raised spa or a vanishing edge should dig by early February. Design and approvals take about four weeks before the dig, so early February is the last practical point to start design.
How do timelines differ in New Braunfels, Boerne, Bulverde and San Antonio?
New Braunfels
Our home base. Lots range from clay to limestone shelf. Master-planned communities such as Vintage Oaks run their own plan review, so submit early.
Boerne
Limestone and sloping lots mean rock excavation and often engineering. Gated communities like Cordillera Ranch review pool plans in detail. Plan for the longer end of the schedule.
Bulverde
Expect limestone shelf on many lots, which adds excavation time. Communities such as Johnson Ranch have an active architectural review committee.
San Antonio
A city permit plus HOA review in communities like Stone Oak and The Dominion. We prepare and submit both.
We build in New Braunfels, Boerne, Bulverde, San Antonio, Canyon Lake, Spring Branch and the surrounding Hill Country. See every neighborhood we build in.
Can a pool be built in winter in Texas?
Yes. Central Texas winters are mild enough to excavate, set steel and shoot gunite through most of the season. We schedule gunite and interior finish work around hard freezes, because both need above-freezing temperatures to cure properly. A winter dig is how most spring and early-summer pools get finished on time.
Permitting is covered step by step in our permits and HOA guide, and line-item pricing is in the pool cost guide.
Questions about timing.
When should I start planning a pool to swim by summer?+
Start design in November or December. That leaves about four weeks for design, engineering, permits and HOA review, a February dig, and enough room for a 10 to 16 week build to finish before Memorial Day, May 31, 2027.
How long does a custom pool take from first call to first swim?+
Plan on about four months. Design, engineering, permits and HOA review take roughly four weeks. Construction takes 10 to 12 weeks on a typical lot, and up to 16 weeks with heavy rock, HOA delays or wet weather.
Can a pool be built in winter in Texas?+
Yes. Central Texas winters are mild enough to excavate, set steel and shoot gunite through most of the season. We schedule gunite and interior finish work around hard freezes, because both need above-freezing temperatures to cure properly.
Does HOA approval slow down a pool build?+
It can add a few weeks, depending on how often the committee meets. HOAs tend to approve faster in the winter months than in peak spring season, when plan submittals pile up, so a winter submittal usually means less delay getting started. We prepare the drawings and the submittal ourselves.
How much does a custom pool cost?+
Custom gunite pools start around $60,000. Most builds run $75,000 to $150,000, and resort-level builds start at $150,000. Every quote is itemized, and financing is available.
Read before you sign.
Get on the spring build schedule.
Tell us where your lot is and when you want to swim. We will tell you honestly whether that date is realistic and what it takes to hit it.
- —Google Guaranteed and BBB accredited, firefighter owned and family operated
- —3D design before anything is built, and an itemized, line-by-line quote
- —We handle city and county permits and your HOA paperwork
- —Rated 5.0 on Google. Read them
Prefer to talk now? Call (830) 244‑7665.
Design now, swim in May.
A first conversation costs nothing and gets your design started.